"We strongly disagree with the Court’s ruling that the wind project must be removed by December 1, 2025," Enel said in a ...
A federal judge ordered the removal of a wind farm from the Osage Nation’s Mineral Estate, concluding a decade-long dispute ...
After a 10-year court battle, a federal judge has ordered the removal of a wind farm on Osage land. The judge also awarded ...
The Osage Minerals Council, an arm of the Osage Nation, sued the wind farm owners in 2014, claiming the operator never ...
U.S. Judge Jennifer Choe-Groves of the U.S. Court of International Trade ended 10 years of litigation involving the Osage ...
Nearly a month after a storm-damaged wind turbine was demolished using explosives on Sally Freeman’s farm, the fallout ...
U.S. District Judge Jennifer Choe-Groves of the U.S. Court of International Trade concluded 10 years of litigation by ...
Vineyard Wind said the work resumed on Saturday and continued through the weekend after the federal Bureau of Safety and ...